    The project still needs to obtain state and federal approvals to develop and build the plant, but organizers anticipate construction to begin in 2015 and operations to begin by 2018.
    The project still needs to obtain state and federal approvals to develop and build the plant, but organizers anticipate construction to begin in 2015 and operations to begin by 2018.
  • WV DEP Lifts Cease Operations Order to Antero at Harrison, Doddridge Sites

    WV DEP Lifts Cease Operations Order to Antero at Harrison, Doddridge Sites

    Monday, April 21 2014 1:00 PM EDT2014-04-21 17:00:50 GMT
    The West Virginia Department of Environmental Protection and the Office of Oil and Gas have issued violation notices to Antero Resources.
    The West Virginia Department of Environmental Protection and the Office of Oil and Gas have issued violation notices to Antero Resources.
  • Fracking foes cringe as unions back drilling boom

    Fracking foes cringe as unions back drilling boom

    Monday, April 21 2014 8:51 AM EDT2014-04-21 12:51:19 GMT
    After early complaints that out-of-state firms got the most jobs, some local construction trade workers and union members in Pennsylvania, Ohio and West Virginia say they're now benefiting in a big way from the Marcellus and Utica Shale oil and gas boom.That vocal support from blue-collar workers complicates efforts by environmentalists to limit the drilling process known as fracking.
    After early complaints that out-of-state firms got the most jobs, some local construction trade workers and union members in Pennsylvania, Ohio and West Virginia say they're now benefiting in a big way from the Marcellus and Utica Shale oil and gas boom.That vocal support from blue-collar workers complicates efforts by environmentalists to limit the drilling process known as fracking.

A new report by federal surface mine regulators obtained by the Sludge Safety Project indicates there are some concern about the way West Virginia coal slurry dams are built.

The concerns indicated by the one-page executive summary of the Office of Surface Mining study, titled "Oversight Report of Compaction of Coal Mine Waste Slurry Impoundment Embankments Evaluation Year 2011," points out four different observations.

The findings indicated materials that compact only at a narrow range of moisture content, coal wastes arrive at the impoundment in a wet condition, operators typically add material in possible non-ideal weather conditions and compaction equipment used is designed for compaction.

"In most cases, the reported compaction equipment is one or more dozers," the report states. "Dozers are not designed to compact soil. The tracks are designed to allow the dozer to operate on loose ground."

The study was designed to test the ability of operators to "consistently able to be adequately compact the coarse refuse under conditions that would appear to be adverse." The materials are intended to settle and compact, failure to do so could threaten the integrity of the slurry dam.

According to the report, OSM engineers had observed consultants recording passing test results, though visual observations "indicate the material may not be adequately compacted."

"Results of the testing tend to indicate that the coarse refuse is not consistently being compacted in accordance with approved specifications," the report states. "Failing field density tests occurred at all seven of the sites investigated."

According to the report, of the 73 field density tests spread over seven sites, only 16 tests passed.

"These results indicate the quality control methods used during embankment construction may not be achieving the desired results," the report states.

According to the Associated Press, an OSM representative said there is no indication there has been any sign of imminent danger of failure at any of the sites.

The failure of coal slurry dams can have devastating results. The failure of a dam filled with the liquid coal wastes sent more than 300 million gallons of slurry into in Martin County, Ky. in October 2000.

The owner of that pond, Massey Energy, spent millions trying to restore the health of the two Tug Fork River tributaries.

The West Virginia Department of Environmental Protection is reviewing the information, but has not yet responded to comment. A group of citizens who obtained the document are having a press conference Thursday morning.